# Silkeborg Varme - Major Overhaul of GE Gas Turbines

- **Source:** TED · `173945-2025`
- **Buyer:** Silkeborg Varme A/S
- **Published:** 2025-03-18
- **Deadline:** —
- **Estimated value:** 4,000,000 EUR
- **CPV codes:** 65000000, 50500000, 65410000
- **NUTS codes:** DK042, DNK
- **Notice type:** can-standard / 30

## Description

SV is planning for a major overhaul of the 40 MW GE gas turbine at the CHP plant in Silkeborg. The turbine was commissioned in 1995. To ensure reliable, safe, and efficient operation of the unit a major overhaul of the Gas turbine is needed.

## Original notice

https://ted.europa.eu/da/notice/-/detail/173945-2025