# Catenary system - Electrification New railway across West Funen

- **Source:** TED · `344288-2025`
- **Buyer:** Banedanmark
- **Published:** 2025-05-28
- **Deadline:** 2025-10-17
- **Estimated value:** 421,500,000 DKK
- **CPV codes:** 45234160, 45230000, 45231400, 45232200, 51100000, 51111300, 51112100, 71311230, 71311300, 71320000, 71322500
- **Place-of-performance NUTS:** DK031, DK022, DNK
- **Buyer-address NUTS:** —
- **Notice type:** cn-standard / 17

## Procedure details

Source lists may span several lots; list positions do not establish relationships.

### Procedure Types

- open

### Award Criterion Names

- Price
- Method of execution
- Organisation
- Process describtion

### Award Criterion Descriptions

- In the evaluation of Price, the total tender price including options (option 1 and option 2) set out in the two Schedules of prices will be used.
- The evaluation of sub-criterion II will be conducted in accordance with the stated in the Tender Specifications.
- The evaluation of sub-criterion III will be conducted in accordance with the stated in the Tender Specifications.
- The evaluation of sub-criterion IV will be conducted in accordance with the stated in the Tender Specifications.

### Options

- The Contract contains 2 options: Option 1. Spare parts The option covers deliverance of spare parts in relation to Banedanmark's maintenance of the catenary system. Option 2: To activate a separate and distinct design and build contract for the project Overhead Contact Line System (OCLS) for a new fly-over zone at Ringsted Station (KURI). The conducted procurement procedure covers the projects “Catenary system, New railway across West Fu-nen” and as an option “Overhead Contact Line System (OCLS) for a new flyover zone at Ringsted Station”. Thus these shall be considered separately and each governed by their own contractual basis. Accordingly activation of option 2 leads to Banedanmark and the Contractor entering into a separate contract. Scope of works for KURI is as follows: • System specification and basic design - developed from the West Funen main contract - of an overhead contact line system (OCLS) for an operational speed of 250 km/h and for 275 km/h in test situation • Installation design for OCLS, return current system, earthing and bonding (E&B) and remote control of line side switch gear • Component delivery • Installation and testing of the complete 25 kV OCLS including return current system, E&B and remote control

### Submission Urls

- https://eu.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=430893&B=

## Description

The Contract comprises the following: • Designing, delivery, building and testing of a TSI approved 25 kV catenary system, including remote control and connection of feeder and return cables, for an operational speed of 250 km/h and for 275 km/h in test situation on the new line across West Funen

## Original notice

https://ted.europa.eu/da/notice/-/detail/344288-2025