# CPH City & Port I/S' (Udviklingsselskabet By & Havn I/S') public procurement procedure concerning supply and installation of a 132/30 kV - 55 MVA - Power Transformer

- **Source:** TED · `339878-2025`
- **Buyer:** Udviklingsselskabet By & Havn I/S (CPH City & Port)
- **Published:** 2025-05-27
- **Deadline:** 2025-08-08
- **Estimated value:** 25,000,000 DKK
- **CPV codes:** 31000000, 31170000
- **Place-of-performance NUTS:** DK011, DNK
- **Buyer-address NUTS:** —
- **Notice type:** cn-standard / 17

## Procedure details

Source lists may span several lots; list positions do not establish relationships.

### Procedure Types

- open

### Award Criterion Names

- Price
- Planning of Works
- Quality, Health, Safety, and Environmental (QHSE)

### Award Criterion Descriptions

- As described in the Tender Conditions section 9.3.1.
- As described in the Tender Conditions section 9.3.2.
- As described in the Tender Conditions section 9.3.3.

### Options

- The Contract has the following options: • Option 1: Upgrade of the Power Transformer from 55 MVA to 68 MVA • Option 2: Storage of the Power Transformer and all accessories • Option 3: Extension of the warranty period with up to 3 times 1 year • Option 4: Additional support on site • Option 5: Supply and installation of a Dissolved Gas Analyzer • Option 6: Supply and installation of an Automatic Voltage Regulator (AVR) panel • Option 7: Current Power Transformer on the HV neutral point connection to earth

### Submission Urls

- https://www.ethics.dk/ethics/eo#/124e9fd1-7483-4128-9199-ee27a1382c68/homepage

## Description

This tender procedure concerns supply and installation of a 132/30 kV – 55MVA – Power Transformer to connect CPH City and Port’s new shoreside power system to the local grid and thereby utilize the full capacity of the purchased shoreside power system. The project includes the design, supply, and installation of a 132/30 kV – 55 MVA – Power Transformer in accordance with the specifications provided by the customer. The Power Transformer will supply power from the local energy grid to the shore power system for cruise ships calling at both Oceankaj in Nordhavn and Langeliniekaj in Copenhagen Inner Harbour. The project includes finalizing of design into a complete execution project, including Design Management and ICT management in accordance with the requirements provided by the customer, and supply and install of all necessary parts of the finalization of a Power Transformer adhering to the functional requirements.

## Original notice