# Tunnel North Contract

- **Source:** TED · `678331-2025`
- **Buyer:** Femern A/S
- **Published:** 2025-10-15
- **Deadline:** —
- **Estimated value:** 1,473,983,887 EUR
- **CPV codes:** 45000000, 45100000, 45200000, 45220000, 45221000, 45221246, 45240000, 45262300, 71000000, 71300000, 71350000, 45262310
- **Place-of-performance NUTS:** DK022, DNK
- **Buyer-address NUTS:** —
- **Notice type:** veat / 25

## Procedure details

Source lists may span several lots; list positions do not establish relationships.

### Procedure Types

- neg-wo-call

### Award Criterion Names

- Technical and Administrative
- Price

### Award Criterion Descriptions

- Weighting: 50

## Description

The Fehmarnbelt Fixed Link Project (‘Project’) is the final stage in the realisation of a straight traffic corridor between Scandinavia and continental Europe. It will be an immersed tunnel containing two dual carriageways and a twin-track railway traversing the 19 km distance across the Fehmarnbelt between Lolland in Denmark and Puttgarden in northern Germany. The immersed tunnel elements will be manufactured at a pre-designated site at Rødbyhavn on Lolland (‘Production Site’). The Principal Contracts are: 1) Tunnel Dredging and Reclamation Contract; 2) Tunnel North Contract; 3) Tunnel South Contract; and 4) Tunnel Portals and Ramps Contract. This notice concerns 2) Tunnel North Contract which was awarded to the consortium, Femern Link Contractors (FLC), consisting of the following members: - Per Aarsleff Holding A/S; - VINCI Construction Grands Projets S.A.S.; - CFE SA; - Soletanche Bachy International S.A.S.; - BAM Infra BV; - BAM International BV; - Wayss & Freytag Ingenieurbau AG; - Max Bögl Stiftung & Co. KG; and - Dredging International NV. For more information regarding the Principal Contracts, see the voluntary ex ante transparency notices of 4 March 2016: 1) Tunnel North Contract: 2016/S 048-079336; 2) Tunnel South Contract: 2016/S 048-079339; 3) Tunnel Portals and Ramps Contract: 2016/S 048-079337); and 4) Tunnel Dredging and Reclamation Contract: 2016/S 048-079338). The Works included in the Tunnel North Contract are fully contained in the published contract notice: 2012/S 192-315514 and voluntary ex-ante transparency notice: 2016/S 048-079336.

## Original notice

https://ted.europa.eu/da/notice/-/detail/678331-2025