TED474986-2024
145 kV GIS substations for Hovegård (HVE)
- Ordregiver
- Energinet Eltransmission A/S
- Værdi
- 11.423.100 EUR
- Frist
- —
- Publiceret
- 7.8.2024
- CPV
- 31000000
- NUTS
- DK012, DNK
Tildeling
Samlet værdi: 11.423.100 EURKontrakt indgået: 9.7.2024
CVR 3985663811.423.100 EUR2 bud modtaget
Beskrivelse
The Contracting Authority wants to purchase one 3 phase, 145 kV, 50 Hz, gasinsulated switchgear (GIS) double busbar for substation Hovegård (HVE) and delivered on Energinet’s site, ready for operation. The GIS Switchgear will be install in a new building - The supply consists of 17 (seventeen) line-feeder bays, 2 (two) transformer bays, 2 (two) bus bar coupler bays, 2 (two) bus bar sub-divider bays and 2 (two) metering bays.