TED785315-2025

Serbia Nis-Presovo Rail project, Geotechnical Investigations and Elaborates for Preliminary Design Studies

Ordregiver
"Western Balkans Investment Framework (WBIF) Infrastructure Project Facility – Technical Assistance 8 (IPF 8)" consortium, represented by COWI A/S (hereinafter: COWI IPF)
Værdi
544.790 EUR
Frist
Publiceret
26.11.2025
CPV
71332000
NUTS
SRB
Tildeling
Beskrivelse
Service Provision Agreement for Geotechnical Investigations and Elaborates for Preliminary Design Studies in the scope of the subproject "WB19-SRB-TRA-03, Orient/East-Med Corridor: Serbia–North Macedonia Corridor X Rail Interconnection, Nis–Presevo–Border Between the Two States Section". Duration: 18 months The works are expected to to be undertaken in the following time periods: • Section A: 5 months • Section B: 5 months (concurrently with sub-section B) • Section C : 5 months from instruction to commence