KFST2885-1
Danmark-Horsens: Kedelinstallationer
- Ordregiver
- Fjernvarme Horsens A/S
- Oplyst værdi / estimat
- —
- Frist
- 1.10.2018
- Publiceret
- 4.9.2018
- Leveringssted (NUTS)
- Ikke oplyst
- Ordregivers adresseområde (NUTS)
- DK04
Dataposten opdateret . Datakilder, dækning og beregningsmetode.
Beskrivelse
Horsens CHP station is a waste incineration plant located at the harbour near the city centre of Horsens. The plant consists of 2 identical 5 t/h waste incineration lines, which were commissioned together in 1992. The scope of works shall comprise a complete exchange of the boiler pressure and flue gas parts from above the existing grate and until the flue gas cleaning system.Also included is the removal of disposal of the old boiler parts, as well as all necessary auxiliary systems and all necessary monitoring and measuring points, etc.The new boilers shall fit into the existing buildings and shall be reincorporated with the other existing/remaining systems.
Andre bekendtgørelser i samme CPV-kategori
Nyeste bekendtgørelser med samme firecifrede CPV-kategori. Listen kan omfatte både åbne udbud og historik.
- Fase I: Indkøb af udstyr til ZBC's procesoperatøruddannelse.
Zealand Business College (ZBC)
- EU-procurement - Competitive procedure with negotiation – Tender for new thermal oil bundles for Renseanlæg Avedøre, Denmark Teknisk afdeling - EU-udbud
BIOFOS A/S
- 40 MW elkedel til Lolland Vand & Energi A/S
Lolland Vand og Energi A/S
- Opførelse af komplet og funktionsdygtig energicentral
I/S Vestforbrænding og datterselskaber
- Superheater outlet steam headers at Avedøre Power Plant in Denmark.
Ørsted Bioenergy & Thermal Power A/S
- 2026 - Procurement of 1,050 filter bags for use at Fjernvarme Fyn
Fjernvarme Fyn Service A/S