KFST5954-1
Danmark-Fredericia: Stærkstrømskabler
- Ordregiver
- Energinet Eltransmission A/S
- Oplyst værdi / estimat
- 59.600.000 DKK
- Frist
- 19.5.2020
- Publiceret
- 6.3.2020
- Leveringssted (NUTS)
- Ikke oplyst
- Ordregivers adresseområde (NUTS)
- DK03
Dataposten opdateret . Datakilder, dækning og beregningsmetode.
Beskrivelse
The contracting authority wants to purchase the complete functional supply of approximately 10 km 145 kV submarine cable system, including all labour, equipment and materials required for design, fabrication, factory testing, supply, construction, transition joints and hang offs, transport of cable to a harbour in Zealand, jointing works, completion and commissioning as a part of a new 145 kV cable system connecting Amager Power Plant (AMV) and Svanemølle substation (SMK).
Andre bekendtgørelser i samme CPV-kategori
Nyeste bekendtgørelser med samme firecifrede CPV-kategori. Listen kan omfatte både åbne udbud og historik.
- Rammeaftale på luftledningsmontage
Energinet Eltransmission A/S
- NEA and SLF02 – Procurement of 400 kV and 132 kV cable systems
Energinet Eltransmission A/S
- 26/11399 - Rammeaftale vedrørende anskaffelse af kabler til datacentre
Energinet
- Signalling system for the Fjernbane East
Banedanmark
- Signalling system for the Fjernbane East
Banedanmark
- Signalling system for the Fjernbane East
Banedanmark